San Antonio Creek- Ojai Valley Trail Bridge

This project was initiated after the trail crossing was damaged and closed by the 2005 floods. At that time, flood waters washed out portions of the trail and rendered impassable for several month. During that period, the historic fair weather crossing was identified as a Steelhead trout passage barrier at the mouth of a Critical Habitat Creek. Regulatory authorization was obtained for temporary repairs while a permanent bridge was pursued.
Several smaller bridge designs were evaluated, but none could meet the regulatory design standard of passing the 100-year flood without causing flooding of surrounding properties or altering the extent of flooding. Alternate crossing locations were also evaluated and found to not reduce the required bridge size. (From Dedication Agenda)

Bridge Dedication Tuesday 3-13-12, 3pm

Bridge dedication 3-13-12

Front Row: CIBC Founding Members Ed & Udas Young, Supervisor Steve Bennett, Theresa Lubin(County Parks Manager) & Leslie Ogden(CIBC President), Back Row: Coastal Comission member, NOAA member, (Ventura County), Peter Shaday(Ventura County Public Works), Unknown, Peter De Hann(Ventura Transportation Commission)

Bridge Sponsors Cut the Ribbon!!

Ojai Valley News article

Bridge Dedication Handout

Content on this page requires a newer version of Adobe Flash Player.

Get Adobe Flash player

Video of a portion of dedication!!


Content on this page requires a newer version of Adobe Flash Player.

Get Adobe Flash player


Video by Ojai Cyclist Brian


Ojai Trail Bridge 3-4-12


Bridge looking good!!

(Updated 3-4-12)


Paved path to new bridge


Ramps paved to new Bridge, temporary fencing down, Bridge is not open at this time!!

(Updated 2-26-12)


Ramp completed to South side of bridge

Ramp completed to South side of bridge, ready to be paved.

(Updated 2-15-12)


view from Ojai Trail Bridge


(updated 2-12-12)


Bridge placed

(Updated 2-2-12)

Bridge at San Antonio Creek on Ojai Trail

(Photos by Theresa Lubin:
Ventura County Parks Manager)

New bridge in the air

We have a Bridge!!

(Photos courtesy of John Brant)


South abutement  with riprap

Progress on Bridge
Forms removed, riprap placed by south abutement!!

(Updated 1-22-12)


Bridge from North on 1-11-12
Progress on Bridge
Major Concrete pours completed, Bridge to arrive Jan 30th!!

(Updated 1-11-12)

Bridge progress 1-4-12

Progress on Bridge
North Pier stripped and pretty, Middle Pier still has forms foundation, South Pier poured but with forms, South Abutement and Headwalls being poured today!

Last Picture from Santa Anna Road shows simulated bridge in place.
(Updated 1-4-12)


Progress on San Antonio Creek Bridge
Progress on Bridge

Two North Piers completed, North Abutement Foundation poured, South Pier and abutement being formed.

(Updated 12-27-11)


Bridge 12-15-11

Progress on Bridge

Bank & Creek restored, piers completed, pier's crossbars being formed.

( 12-15-11)

Progress on San Antonio Creek

2 Bridge piers in & starting to remove concrete!

( 11-16-11)


San Antonio Creek Crossing before bridge project

(Original)

Ojai Valley Trail is now closed for San Antonio Bridge Project


Contract awarded for Ojai Valley Trail bridge; closure in mid-October
(updated 9-30-11)


Here is the PDF of the bridge design: It will be a board plank deck 12 ft. wide by 480 ft. long

 


bicyclist on low water crossing of San Antonio creek
Board closes funding gap for bridge on Ojai Valley Trail
Read more:

CIBC has contributed $20K towards this project


 

 