San Antonio Creek- Ojai Valley Trail Bridge
This project was initiated after the trail crossing was damaged and closed by the 2005 floods. At that time, flood waters washed out portions of the trail and rendered impassable for several month. During that period, the historic fair weather crossing was identified as a Steelhead trout passage barrier at the mouth of a Critical Habitat Creek. Regulatory authorization was obtained for temporary repairs while a permanent bridge was pursued.
Several smaller bridge designs were evaluated, but none could meet the regulatory design standard of passing the 100-year flood without causing flooding of surrounding properties or altering the extent of flooding. Alternate crossing locations were also evaluated and found to not reduce the required bridge size. (From Dedication Agenda)
Bridge Dedication Tuesday 3-13-12, 3pm

Front Row: CIBC Founding Members Ed & Udas Young, Supervisor Steve Bennett, Theresa Lubin(County Parks Manager) & Leslie Ogden(CIBC President), Back Row: Coastal Comission member, NOAA member, (Ventura County), Peter Shaday(Ventura County Public Works), Unknown, Peter De Hann(Ventura Transportation Commission)
Bridge Sponsors Cut the Ribbon!!
Video of a portion of dedication!!
Video by Ojai Cyclist Brian
Bridge looking good!!
(Updated 3-4-12)
Ramps paved to new Bridge, temporary fencing down, Bridge is not open at this time!!
(Updated 2-26-12)
Ramp completed to South side of bridge, ready to be paved.
(Updated 2-15-12)
(updated 2-12-12)
(Photos by Theresa Lubin:
Ventura County Parks Manager)
We have a Bridge!!
(Photos courtesy of John Brant)
Progress on Bridge
Forms removed, riprap placed by south abutement!!
(Updated 1-22-12)

Progress on Bridge
Major Concrete pours completed, Bridge to arrive Jan 30th!!
Progress on Bridge
North Pier stripped and pretty, Middle Pier still has forms foundation, South Pier poured but with forms, South Abutement and Headwalls being poured today!
Last Picture from Santa Anna Road shows simulated bridge in place.
(Updated 1-4-12)
Progress on Bridge
Two North Piers completed, North Abutement Foundation poured, South Pier and abutement being formed.
(Updated 12-27-11)
Bank & Creek restored, piers completed, pier's crossbars being formed.
( 12-15-11)2 Bridge piers in & starting to remove concrete!
( 11-16-11)
(Original)
Ojai Valley Trail is now closed for San Antonio Bridge Project
Contract awarded for Ojai Valley Trail bridge; closure in mid-October
(updated 9-30-11)
Here is the PDF of the bridge design: It will be a board plank deck 12 ft. wide by 480 ft. long
Board closes funding gap for bridge on Ojai Valley Trail
Read more:
CIBC has contributed $20K towards this project